Construction Program

Stage 1 (Corner Site)

Foundations: April & May ‘07
Precast Walls & beams: June
Suspended Floor Slabs: July & August
Structural Steelwork: September
Roofing: September & October
Internal Partitioning: October
Services: September, October, November
External Works: December, January ‘08
Fit-out: January, February ‘08
Finishes: February, March
Commissioning: April ‘08

Stage 2 (Staff Offices – existing building)

New Partitions, doors: February, March & April ‘08
Air-conditioning: April ‘08

Stage 3 (Carpark extension & modifications)

Demolish both houses: March ‘08
Remove trees, change Court levels: April, May ‘08
Asphalting, new gardens, trees, etc: June, July ‘08